How to coordinate an office move
A smooth office move is mostly a planning job done weeks before anyone lifts a box. This is a working timeline: who should own what, what to do at each stage and how to run the day itself.

Name one owner and set the date
Every office move needs one person who owns it. It does not have to be a director or an office manager, but it must be someone with the time, the authority to make decisions and the habit of following things up. Without an owner, tasks sit between departments and quietly do not happen.
Give that person a small group to work with: someone from IT or whoever looks after the systems, someone from finance or admin for contracts and addresses, and a representative from each team who can speak for their area. The group does not need long meetings, only a short regular check-in and a shared list.
Then fix the date. Work back from lease dates, notice periods and the dates on which the new premises are available. Allow for a gap between getting the keys and moving in, so that cabling, cleaning, a fit-out or repairs can happen first. Weekends and quieter points in your trading year tend to be easiest, though specific timings, such as out-of-hours work, are not something this site can confirm.
For help choosing a mover, see our guide to choosing office removals services, which covers scoping and comparing quotes.
A timeline from the first month to move day
The right lead time depends on the size of the office, but this shape works for most. Adjust the weeks to suit.
- Eight to twelve weeks out: confirm the date, appoint the owner, take stock of what you have, and measure the new space. Notify the landlord of your intention to leave if required.
- Six to eight weeks out: ask for quotes, compare them and confirm the booking. Plan the layout for the new office and work out which furniture is going and which is not.
- Four to six weeks out: brief staff, start clearing and archiving, order any new furniture, and arrange for broadband, voice lines and any systems to be installed at the new site.
- Two to four weeks out: start packing the things nobody uses daily, label everything, and tell customers, suppliers and the bank about the new address.
- The last week: confirm everything with the mover, finish packing, walk the route, and check that the new site is ready.
- Move day, and the week after: run the day, check the equipment works, and sort out what is missing.
Put each task on a shared list with a name and a date next to it. A list that everyone can see is the simplest piece of project management there is, and it stops the same questions being asked three times.
Get the quote and the access details right
On this site, an office move is a Full Removals quote request. List the desks, cabinets, shelving and heavy items in the bulky item list, give an estimate of the boxes, say whether you need packing and materials, and add notes on floors, lifts and parking at both ends. The Van Man Co replies with a quote, nothing is booked until you accept it, and the quote confirms availability for the route.
A video walkthrough of both buildings, from the entrance to the furthest desk, makes the quote more accurate and often shows up access problems early. Our office removals page has more on what to include.
Check access rules in both buildings. Many landlords and managing agents require lifts to be booked, loading areas to be reserved, floor protection to be used and insurance details to be given in advance. On a busy street in the town centre, the vehicle needs a legal parking space, and BCP Council's contractors parking dispensation for the Bournemouth area is applied for online at least three days ahead.
Send the mover the access details and the contact for the building. Ask for the plan for the day in writing, covering arrival time, numbers and order of work.
Brief staff and keep them in the loop
People are the main source of both help and friction in an office move. Tell everyone the date and the plan as early as you can, then keep telling them. A short message each week, saying what has been done and what is next, prevents rumours and means people can plan their own work.
Give each person a clear job. Everyone should know what to pack, by when, how to label it, and what to take home or carry themselves, such as laptops, personal items and anything valuable. Provide boxes in good time and a simple labelling system, with the destination desk or room on every box, not just the owner's name.
Decide how the working week of the move will run. If some people will work from home on the day, say so, and make sure they have what they need. If the office has to be open to customers, work out how to cover incoming enquiries while the move is under way.
Think about people's concerns as well as their tasks. A new location changes the commute, parking and lunch options, and a short note about the new area, the transport and the first-day arrangements helps people settle.
Labelling, packing and the move-day plan
Good labelling is the difference between an office that is working by lunchtime and one that spends a week hunting for cables. Use a clear system: a colour or zone code for each area of the new office, a number for each box and a list that links numbers to desks. Put labels on two sides of every box, not on the lid.
Make a floor plan of the new office, mark where each desk and piece of furniture goes, and share it with the mover and your own staff. Put matching labels on the furniture so that it can be put straight into place, not stacked in the middle of the room.
On the day, make sure the owner or a deputy is at each site, with the plan and a list of contacts. One person at the old office checks that everything has gone and nothing is left behind, and another at the new office directs the furniture and boxes. Keep a basic kit to hand: tape, markers, scissors, a first-aid kit, water and device chargers.
Keep valuables and critical items out of the move. Laptops, backups, documents, keys and anything confidential should be carried by trusted people. Whether the mover handles file archives or IT equipment is something to ask in the quote request, not to assume, and your own IT supplier should handle any systems that need disconnecting and reconnecting.
Tell the world your new address
A new address touches many things, and it is easy to forget some of them. Work through a list in the weeks before the move, and update the most important records first. This includes your website, signature blocks, letterheads, invoices, business cards, insurance policies, bank, accountant, utilities and licences.
If you are a company and your registered office is changing, Companies House needs to be told, and the same goes for other registers and regulators relevant to your business. Do this through the official channels, not through a third party, and check the details carefully.
Set up a postal redirection, such as Royal Mail's redirection service, for a period after the move, so that nothing is lost while people catch up with the change. Tell your customers and suppliers in advance, and put a notice on your website and in your signature blocks a few weeks before the date.
Do not forget the quieter updates: online listings, maps, directories, social profiles and anything that appears in search. A wrong address on a map listing can send customers to the old building long after you have gone.
After the move: settle in and close out
On the first morning, check that the essentials work: power, broadband, voice lines, printers, the door entry and the heating. Have a named person who deals with problems, and make it easy for staff to report them. A shared list of snags, worked through in order, is better than people fixing things in their own way.
Unpack in priority order. Get the main workstations and systems running first, then shared areas, then storage. Keep the boxes in one place until they are collected, and keep the labels, because they help you find missing items.
Close out the old premises properly. Check that it is empty and clean, return keys and passes, take final meter readings, and agree on any condition issues with the landlord. Photographs of the state of the space on departure are a sensible record.
A week or two later, hold a short review. Ask what worked, what did not and what to do differently, and note the answers for next time. If you want more on keeping the business running through the move, our post on minimising business disruption goes into it. When you are ready to describe your move, use the price section on this page.